December 2024 Update
All remaining elevators will be inspected by the second week of January 2025.
Elevator #2 COMPLETE
Elevator #11 COMPLETE
Elevator #13 COMPLETE Awaiting Inspection
Phase 2
Elevator #3 COMPLETE
Elevator #5 COMPLETE Under Repair
Freight Elevator #12 COMPLETE
Phase 3
Elevator #1 COMPLETE
Elevator #4 COMPLETE Awaiting Inspection
Elevator #6 COMPLETE Awaiting Inspection
The remaining elevator lobby VCT tile replacement will be completed in January 2025 as well.
We appreciate your patience as we welcome these much-needed improvements to the North Academic Center infrastructure.
Last Updated: 01/08/2025 15:00