FIRST RENOVATED ELEVATOR BACK IN OPERATION!!!!
This month the project proceeds with Phase 1 and Phase 2. Phase 3 is expected to start next month.
Phase 1
Elevator #2 is the passenger in Bank A on the south side of the building (Aronow Theater). This elevator is expected to return to operation April 16th.
Elevator #11 is the service elevator in the north side of the building near the loading docks. This elevator is expected to return to operation in May.
Elevator #13 is the service elevator that services the cafeteria kitchen. This elevator is expected to return to operation in May.
Phase 2
Elevator #3 is the passenger elevator in Bank B by the Public Safety office. This elevator is expected to return to operation in May.
Elevator #5 is the passenger elevator in Bank C by Career Service.
Freight Elevator #12
Phase 3
Elevator #1 is the passenger in Bank A on the south side of the building (Aronow Theater). This elevator will be down for replacement after Elevator #2 is returned to operation this month.
Renovation on the remaining elevators is expected to finish around the beginning of the Fall Semester 2024.
Note: For the duration of the project, there will never be both elevators in the same bank under construction at the same time. There will be a maximum of 3 passenger elevators out of service for replacement at a time.
We appreciate your patience as we welcome these much-needed improvements to the North Academic Center infrastructure.