We anticipate the following activities for the month of November:

Start of excavation/support for monumental stair and elevator. Start installation of the new concrete curbs for west guard railings, planters and possible new NAC Bridge stairs. Demolition work is expected to be completed by the end of this month.

Pedestrian access to the Plaza remains restricted for emergency use only until further notice.

Thank you for your patience as we continue to improve the building infrastructure on our campus.  We are doing everything possible to keep the inconvenience and disruption to a minimum.